Scope of Work
The modernized facility will be home to the college’s Allied Health and Nursing Facilities. GTC is providing the Technology Design and Procurement of equipment.
Description
| Project Phase | Anticipated Completion Date |
|---|---|
| Pre-design, design, and document preparation | Summer 2014 |
| Bid process and construction bonding | Fall 2014 |
| Vacate Founders Hall for construction | December 2014 |
| Construction occurs | January 2015 till mid to late 2016 |